Delayed Tasks Summary

The Delayed Tasks Summary report helps identify the tasks which have exceeded their Expected End Dates.

To view this report, you can go to:

Home > Projects > Reports > Delayed Tasks Summary

The report is generated based on the Task Doctype.

Delayed Tasks Summary

Calculation of Delay

Tasks have a date field called Completed On, which becomes visible when a Tasks status is changed to Completed.

Scenario 1

If a task is marked as Completed and the Completed On field is set, then the delay is calculated as the difference between the Completed On and the Expected End Date.

Delay = Completed On - Expected End Date

Scenario 2

If the Completed On field is not set, then the delay is calculated as the difference between the current date and the Expected End Date.

Delay = Current Date - Expected End Date

Chart

The chart shows the number of tasks that are On Track or Delayed based on the report generated after applying the filters.